Capacity planning answers a simple question with real consequences: can this team take on this work? Getting it wrong either burns people out or leaves paid hours unused.
The basic calculation
Available hours = people × working hours − leave − holidays − non-project time
8 people × 160 hours = 1,280 hours. Subtract 64 hours of leave and 192 hours of internal work, and about 1,024 hours are left for project work this month.
Doing it well
- Use actual hours from time tracking, not estimates.
- Take approved leave and holidays into account before assigning work.
- Keep a buffer for support work and surprises.
- Rebalance work across teams before deciding to hire.
In BeeWorkforceIn development
A dedicated capacity view comparing each team's available hours after leave and holidays with assigned work is in development in BeeWorkforce. Today, Wellness shows who is overburdened or underused, and timesheets show hours per project and person. It's part of BeeWorkforce's workforce management software.